Jordan's Grove Road Bridge Replacement

◄ Back
February 11, 2019 2:11 PM

Jordan's Grove Road Project Update

The bridge replacement project on Jordans Grove Road was let on March 19, 2019 and the project was awarded to A.M. Cohron & Sons, Inc. of Atlantic, Iowa for a cost of $1,969,450.47. The bridge is over the Wapsipinicon River and a project schedule is not known at this time.

Facebook Twitter Email

Latest Update:

May 3, 2019 8:39 AM

The contractor plans to start construction this fall. They want to mobilize in late September or early October. The project is expect to be completed in April or May 2020.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

May 3, 2019 8:39 AM

The contractor plans to start construction this fall. They want to mobilize in late September or early October. The project is expect to be completed in April or May 2020.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 3, 2019 8:39 AM

The contractor plans to start construction this fall. They want to mobilize in late September or early October. The project is expect to be completed in April or May 2020.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)